Vertical steel tanks for D.Tek

Development of KM/KMD, production of the tank, delivery, installation, anti-corrosion cleaning with sandblasting inside and outside

Location

with. Semerinky, Poltava region

volume

2x700

Appointment

Hydrocarbon gas concentrate

Material

Steel 3

From application to delivery

55 days

The implementation of the project began with the development of design documentation (km/kmd), which allowed to process in detail all the technical parameters of two vertical steel tanks with a volume of 2 × 700 m³. In the manufacturing process, steel 3 was used, which provides high strength and resistance to hydrocarbon gas concentrate. All welding seams were thoroughly monitored to guarantee tightness of the structure.

The next step was the delivery and installation of tanks on the object. Specialized transport allowed to transport large structures safely, and installation work was performed with the use of hoisting equipment. Much attention was paid to the accuracy of the connection of the elements, which ensured the stability and durability of structures.

The final stage was the protective coating of tanks. The internal and outer surface was cleaned by sandblasting method, after which an anti -corrosion coating is applied, which guarantees the durability of tanks even in an aggressive environment. All works were completed within a specified period - 55 days. Thanks to the integrated approach, the project was successfully implemented taking into account all safety requirements and operational standards.